Program Updates
Project Facts and Figures:
- 1,476 total proposed homes
- Proposed totals: 547 new homes and 929 renovations
- 547 new, 530 minor, 399 major renovations slated
- Munson Heights — all new homes proposed
- Allen Heights — a combination of new homes and minor renovations
- Bowden Terrace — a combination of new and major renovations
- Silver Wings — a new neighborhood comprised of 15 homes adjacent to the Silver Wings Golf Course
Project Timeline
- January 2006 - Notice to Transition
- April 1, 2006 - Assume Housing Operations
- Late summer 2006 - Construction slated to begin
- April 2007 - First new home completed
- January 2008 - Site work began on the Allen Heights Neighborhood Center
- February 2008 - Site work began on Silver Wings, a Senior Grade Officer neighborhood with 15 planned homes off Hatch
Road.
- June 30, 2008 - Silver Wings Street Dedication Ceremony for Crandall Court and Freeman Lane
- July 2008 - Silver Wings foundation work begins
- August 2008 - Allen Heights Neighborhood Center Foundation work begins
- January 2009 - First four Silver Wings homes slated for completion
- Summer 2009 - Allen Heights Neighborhood Center Grand Opening
- December 2009 - Silver Wings slated for completion
|